羅茨風(fēng)機(jī)安裝驗(yàn)收→羅茨風(fēng)機(jī)啟動(dòng)柜接線檢查并將轉(zhuǎn)換開關(guān)切換手動(dòng)檔→開啟羅茨風(fēng)機(jī)出風(fēng)管閥門→點(diǎn)動(dòng)羅茨風(fēng)機(jī)檢查風(fēng)機(jī)轉(zhuǎn)向→啟動(dòng)羅茨風(fēng)機(jī)→檢查風(fēng)機(jī)運(yùn)行情況→檢查風(fēng)管出風(fēng)情況(可觀察反沖洗出風(fēng))→檢查出風(fēng)管壓力變送器和機(jī)械壓力表壓力變化→停機(jī)→將風(fēng)機(jī)啟動(dòng)柜轉(zhuǎn)換開關(guān)切換自動(dòng)→在PLC面板或中控室操作站啟/停羅茨風(fēng)機(jī)→將現(xiàn)場(chǎng)控制柜轉(zhuǎn)換開關(guān)切換停止檔→啟停風(fēng)機(jī)應(yīng)無效
Installation and acceptance of Roots blower → check the wiring of Roots blower starting cabinet and switch the change-over switch to manual gear → open the outlet pipe valve of Roots blower → jog the Roots blower to check the direction of the blower → start the Roots blower → check the operation of the blower → check the air outlet of the air duct (observe the backwash air outlet) → Check the pressure change of the outlet pipe pressure transmitter and the mechanical pressure gauge → stop → switch the switch of the fan starting cabinet to automatic → start/stop the Roots blower at the PLC panel or the central control room operation station → switch the switch of the field control cabinet to the stop position → start/stop the blower should be invalid
(1)風(fēng)機(jī)試運(yùn)轉(zhuǎn)前,應(yīng)符合下列要求:
(1) Before the fan test run, the following requirements shall be met:
1)軸承箱和油箱應(yīng)經(jīng)清洗潔凈,、檢查合格后,,加注潤滑油;加注潤滑油的規(guī)格,、數(shù)量應(yīng)符合隨機(jī)技術(shù)文件的規(guī)定,;
1) The bearing box and oil tank shall be cleaned and checked to be qualified before lubricating oil is added; The specification and quantity of lubricating oil shall comply with the provisions of the accompanying technical documents;
2)電動(dòng)機(jī)、汽輪機(jī)和尾氣透平機(jī)等驅(qū)動(dòng)機(jī)器的轉(zhuǎn)向應(yīng)符合隨機(jī)技術(shù)文件的要求,;
2) The steering of drive machines such as motors, steam turbines and tail gas turbines shall meet the requirements of the accompanying technical documents;
3)盤動(dòng)風(fēng)機(jī)轉(zhuǎn)子,,不得有摩擦和碰刮;
3) Turn the fan rotor without friction and scratch;
4)潤滑系統(tǒng)和液壓控制系統(tǒng)工作應(yīng)正常,;
4) The lubrication system and hydraulic control system shall work normally;
污水處理羅茨風(fēng)機(jī)
Roots blower for sewage treatment
5)風(fēng)機(jī)的和連鎖報(bào)警與停機(jī)控制系統(tǒng)應(yīng)經(jīng)模擬試驗(yàn),,并應(yīng)符合下列要求:
5) The safety and interlock alarm and shutdown control system of the fan shall undergo simulation test and meet the following requirements:
a)冷卻系統(tǒng)壓力不應(yīng)低于規(guī)定的值;
a) The cooling system pressure shall not be lower than the specified minimum value;
b)潤滑油的油位和壓力不應(yīng)低于規(guī)定的值,;
b) The oil level and pressure of lubricating oil shall not be lower than the specified minimum value;
c)軸承的溫度和溫升不應(yīng)高于規(guī)定的值,;
c) The temperature and temperature rise of the bearing shall not be higher than the specified maximum value;
d)軸承的振動(dòng)速度有效值或峰-峰值不應(yīng)超過規(guī)定值;
d) The effective value or peak-to-peak value of bearing vibration speed shall not exceed the specified value;
e)喘振報(bào)警和氣體釋放裝置應(yīng)靈敏,、正確,、可靠;
e) The surge alarm and gas release device shall be sensitive, correct and reliable;
f)風(fēng)機(jī)運(yùn)轉(zhuǎn)速度不應(yīng)超過規(guī)定的速度,。
f) The operating speed of the fan shall not exceed the specified maximum speed.
6)機(jī)組各輔助設(shè)備應(yīng)按隨機(jī)技術(shù)文件的規(guī)定進(jìn)行單機(jī)試運(yùn)轉(zhuǎn),,且應(yīng)合格;
6) Each auxiliary equipment of the unit shall be subject to single unit test run according to the provisions of the accompanying technical documents and shall be qualified;
7)風(fēng)機(jī)傳動(dòng)裝置的外露部分,、直接連通大氣的進(jìn)口,,其防護(hù)罩(網(wǎng))應(yīng)安裝完畢;
7) The protective cover (net) of the exposed part of the fan transmission device and the inlet directly connected to the atmosphere shall be installed;
8)主機(jī)的進(jìn)氣管和與其連接的有關(guān)設(shè)備應(yīng)清掃潔凈,。
8) The intake pipe of the main engine and related equipment connected to it shall be cleaned.
This article is published by Roots blower for sewage treatment in Zhejiang Province. Do you know something about these contents? For more information, please click: http://ailelejlb.com We will have more wonderful content waiting for you to check.